Model and Algorithm for Human Resource-Constrained R&D Program Scheduling Optimization

Table 8

The optimal scheduling scheme of traditional MRCPSP.

ActivityStaff combinationActivity durationCostEarliest start time - Earliest finish time

a112 Standard staff75600-7
a122 Standard staff97200-9
a133 Standard staff129609-21
a142 Standard staff1080021-31
b212 Standard staff1915200-19
b222 Standard staff129607-19
b232 Standard staff1296021-33
b243 Standard staff14112019-33
b252 Standard staff13104033-46