Model and Algorithm for Human Resource-Constrained R&D Program Scheduling Optimization
Table 9
The optimal scheduling scheme of special MRCPSP.
| Activity | Staff combination | Activity duration | Cost | Earliest start time - Earliest finish time |
| a11 | 8,9 | 4 | 664 | 0-4 | a12 | 1,6 | 6 | 960 | 0-6 | a13 | 1,6,7 | 11 | 2761 | 6-17 | a14 | 4,11 | 7 | 2004 | 32-39 | b21 | 2,10 | 17 | 2244 | 0-17 | b22 | 9,12 | 12 | 1730 | 4-16 | b23 | 1,3,10 | 10 | 3540 | 17-27 | b24 | 2,5 | 15 | 1368 | 17-32 | b25 | 10,11 | 8 | 1064 | 32-40 |
|
|