Multiobjective Optimization Method for the Diversion Scheme of Lean Concrete Overtopped Cofferdam under Multiconstraint Conditions
Table 6
Characteristics of noninferior solution diversion schemes.
| Diversion scheme | Diameter of the diversion tunnel (m) | Weir height of the cofferdam (m) | Required free float time (d) | Construction cost (104¥) | Construction time of cofferdam (d) |
| 1 | 9.6 | 32.2 | 3 | 11649.37 | 60 | 2 | 9.7 | 31.6 | 7 | 11727.52 | 57 | 3 | 9.8 | 31.0 | 10 | 11809.88 | 55 | 4 | 9.9 | 30.5 | 13 | 11896.09 | 53 | 5 | 10.0 | 30.0 | 16 | 11985.76 | 51 | 6 | 10.1 | 29.5 | 19 | 12078.59 | 49 | 7 | 10.2 | 29.1 | 21 | 12174.26 | 48 | 8 | 10.3 | 28.7 | 23 | 12272.50 | 46 | 9 | 10.4 | 28.3 | 25 | 12373.05 | 45 | 10 | 10.5 | 28.0 | 27 | 12475.67 | 44 |
|
|