International Journal of Manufacturing Engineering
Volume 2013, Article ID 930920, 7 pages
http://dx.doi.org/10.1155/2013/930920
Research Article

A Branch and Bound Approach to Solve the Preemptive Resource Leveling Problem

Faculty of Industrial and Mechanical Engineering, Islamic Azad University, Qazvin Branch, P.O. Box 34185-14161, Qazvin, Iran

Received 10 March 2013; Accepted 5 September 2013

Academic Editors: A. Che, G. Dessein, A. Lockamy, and G. Onwubolu

Copyright © 2013 Behrouz Afshar-Nadjafi et al. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.

Linked References

  1. A. A. B. Pritsker, L. J. Watters, and P. M. Wolfe, “Multi-project scheduling with limited resources: a zero-one programming approach,” Management Science, vol. 16, no. 1, pp. 93–108, 1969. View at Google Scholar · View at Scopus
  2. L. A. Kaplan, Resource-constrained project scheduling with preemption of jobs [Ph.D. thesis], University of Michigan, 1988.
  3. R. A.-V. Olaguíbel and J. T. Goerlich, “The project scheduling polyhedron: dimension, facets and lifting theorems,” European Journal of Operational Research, vol. 67, no. 2, pp. 204–220, 1993. View at Google Scholar · View at Scopus
  4. R. Klein and A. Scholl, “Computing lower bounds by destructive improvement: an application to resource-constrained project scheduling,” European Journal of Operational Research, vol. 112, no. 2, pp. 322–346, 1999. View at Google Scholar · View at Scopus
  5. J. Blazewicz, J. K. Lenstra, and A. H. G. R. Kan, “Scheduling subject to resource constraints: classification and complexity,” Discrete Applied Mathematics, vol. 5, no. 1, pp. 11–24, 1983. View at Google Scholar · View at Scopus
  6. A. Kastor and K. Sirakoulis, “The effectiveness of resource levelling tools for Resource Constraint Project Scheduling Problem,” International Journal of Project Management, vol. 27, no. 5, pp. 493–500, 2009. View at Publisher · View at Google Scholar · View at Scopus
  7. L. V. Tavares, “A review of the contribution of Operational Research to Project Management,” European Journal of Operational Research, vol. 136, no. 1, pp. 1–18, 2002. View at Publisher · View at Google Scholar · View at Scopus
  8. H. N. Ahuja, Construction Performance Control By Networks, John Wiley & Sons, 1976.
  9. S. M. Easa, “RL in construction by optimization,” Journal of Construction Engineering and Management, vol. 115, pp. 302–316, 1989. View at Google Scholar
  10. M. Bandelloni, M. Tucci, and R. Rinaldi, “Optimal resource leveling using non-serial dyanamic programming,” European Journal of Operational Research, vol. 78, no. 2, pp. 162–177, 1994. View at Google Scholar · View at Scopus
  11. E. Demeulemeester, “Minimizing resource availability costs in time-limited project networks,” Management Science, vol. 41, pp. 1590–1598, 1995. View at Google Scholar
  12. M. A. Younis and B. Saad, “Optimal resource leveling of multi-resource projects,” Computers and Industrial Engineering, vol. 31, no. 1-2, pp. 1–4, 1996. View at Google Scholar · View at Scopus
  13. H. Nübel, “A branch-and-bound procedure for the resource investment problem with generalized precedence constraints,” Tech. Rep. WIOR-516, 1998. View at Google Scholar
  14. E. Demeulemeester and W. Herroelen, Project Scheduling A Research Handbook, 2002.
  15. T. Gather, J. Zimmermann, and J.-H. Bartels, “Exact methods for the resource levelling problem,” Journal of Scheduling, vol. 14, no. 6, pp. 557–569, 2011. View at Publisher · View at Google Scholar · View at Scopus
  16. K. Neumann and J. Zimmermann, “Heuristic methods for resource-constrained project scheduling with regular and non-regular objective functions and schedule-dependent time windows,” in Project Scheduling: Recent Models, Algorithms, and Applications, J. Weglarz, Ed., pp. 261–287, Kluwer Academic Publishers, Boston, Mass, USA, 1999. View at Google Scholar
  17. K. Neumann and J. Zimmermann, “Procedures for resource leveling and net present value problems in project scheduling with general temporal and resource constraints,” European Journal of Operational Research, vol. 127, no. 2, pp. 425–443, 2000. View at Publisher · View at Google Scholar · View at Scopus
  18. E. Coughlan, M. Lübbecke, and J. Schulz, “A branch-and-price algorithm for multi-mode resource leveling,” in Experimental Algorithms, vol. 6049 of Lecture Notes in Computer Science, pp. 226–238, 2010. View at Google Scholar
  19. K. Brinkmann and K. Neumann, “Heuristic procedures for resource-constrained project scheduling with minimal and maximal time lags: the resource-leveling and minimum project duration problems,” Journal of Decision Systems, vol. 5, pp. 129–155, 1996. View at Google Scholar
  20. K. Neumann and J. Zimmermann, “Resource levelling for projects with schedule-dependent time windows,” European Journal of Operational Research, vol. 117, no. 3, pp. 591–605, 1999. View at Publisher · View at Google Scholar · View at Scopus
  21. D. Savin, S. Alkass, and P. Fazio, “Construction resource leveling using neural networks,” Canadian Journal of Civil Engineering, vol. 23, no. 4, pp. 917–925, 1996. View at Google Scholar · View at Scopus
  22. D. Savin, S. Alkass, and P. Fazio, “A procedure for calculating the weight-matrix of a neural network for resource leveling,” Advances in Engineering Software, vol. 28, no. 5, pp. 277–283, 1997. View at Google Scholar · View at Scopus
  23. J. J. Moder and C. R. Phillips, Project Management with CPM and PERT, Van Nostrand Reinhold, 1970.
  24. J. J. Moder, C. R. Phillips, and E. W. Davis, Project Management With CPM, PERT and Project Diagramming, Van Nostrand Reinhold, 1983.
  25. R. B. Harris, Precedence and Arrow Networking Techniques for Construction, John Wiley & Sons, 1978.
  26. R. B. Harris, “Packing method for resource leveling (pack),” Journal of Construction Engineering and Management, vol. 116, no. 2, pp. 331–350, 1990. View at Google Scholar · View at Scopus
  27. M. Takamoto, N. Yamada, Y. Kobayashi, H. Nonaka, and S. Okoshi, “Zero-one quadratic programming algorithm for resource leveling of manufacturing process schedules,” Systems and Computers in Japan, vol. 26, no. 10, pp. 68–76, 1995. View at Google Scholar · View at Scopus
  28. E. L. Demeulemeester and W. S. Herroelen, “An efficient optimal solution procedure for the preemptive resource-constrained project scheduling problem,” European Journal of Operational Research, vol. 90, no. 2, pp. 334–348, 1996. View at Google Scholar · View at Scopus
  29. J. H. Patterson, R. Slowinski, F. B. Talbot, and J. Weglarz, “An algorithm for a general class of precedence and resource constrained scheduling problems,” Advances in Project Scheduling, vol. 187, pp. 3–28, 1989. View at Google Scholar
  30. A. Sprecher, Resource-Constrained Project Scheduling—Exact Methods For the Multi-Mode Case, Lecture Notes in Economics and Mathematical Systems, 1994.
  31. J. P. Stinson, E. W. Davis, and B. M. Khumawala, “Multiple resource-constrained scheduling using branch-and-bound,” AIIE Trans, vol. 10, no. 3, pp. 252–259, 1978. View at Google Scholar · View at Scopus
  32. E. Demeulemeester and W. S. Herroelen, “A branch-and-bound procedure for the multiple resource-constrained project scheduling problem,” Management Science, vol. 38, pp. 1803–1818, 1992. View at Google Scholar
  33. G. Igelmund and F. J. Radermacher, “Preselective strategies for the optimization of stochastic project networks under resource constraints,” Networks, vol. 13, no. 1, pp. 1–28, 1983. View at Google Scholar · View at Scopus
  34. B. De Reyck and W. Herroelen, “A branch-and-bound procedure for the resource-constrained project scheduling problem with generalized precedence relations,” European Journal of Operational Research, vol. 111, no. 1, pp. 152–174, 1998. View at Google Scholar · View at Scopus
  35. B. Afshar-Nadjafi, H. Najjarbashi, and E. Mehdizadeh, “A branch-and-bound procedure for RL in multi-mode resource constraint project scheduling problem,” Research Journal of Recent Sciences, vol. 1, no. 7, pp. 33–38, 2012. View at Google Scholar
  36. F. Ballestín, V. Valls, and S. Quintanilla, “Pre-emption in resource-constrained project scheduling,” European Journal of Operational Research, vol. 189, no. 3, pp. 1136–1152, 2008. View at Publisher · View at Google Scholar · View at Scopus
  37. F. Ballestín, V. Valls, and S. Quintanilla, “Scheduling projects with limited number of preemptions,” Computers and Operations Research, vol. 36, no. 11, pp. 2913–2925, 2009. View at Publisher · View at Google Scholar · View at Scopus
  38. M. Vanhoucke and D. Debels, “The impact of various activity assumptions on the lead time and resource utilization of resource-constrained projects,” Computers and Industrial Engineering, vol. 54, no. 1, pp. 140–154, 2008. View at Publisher · View at Google Scholar · View at Scopus