Optimal Design Method of a Hybrid CSP-PV Plant Based on Genetic Algorithm Considering the Operation Strategy

Table 5

Cost estimation of the CSP plant and PV system.

CSP direct costCSP annual cost

Solar field cost (CSF)240 $/m2 of collector areaO&M annual cost1.5%
Piping cost (CPIP)36 $/m2 of collector areaInsurance annual cost0.5%
Tank cost (CTES)750 $/m3 of storage volumePV annual cost
BoP cost (CCSP,BoP)300 $/kWeO&M annual cost1.5%
PV direct costInsurance annual cost0.25%
Panel cost (CPV)1200 $/kWpCSP/PV indirect cost
Inverter cost (CINV)240 $/kWLand cost (CLAND)12 $/m2
BoP cost (Cpv,BoP)240 $/kWEngineering cost (CEPC)20%
Battery cost (CB)1200 $/kWhOther assumption
PV degradation rate0.6%Annual interest rate7%
Operating lifetime25 yearsCSP degradation rate0.2%