Uncertainty Analysis of Energy Production for a 3 × 50 MW AC Photovoltaic Project Based on Solar Resources
Table 8
Energy assessment results through simulation.
| Software | PVSYST V6.47 |
| Project | 3 × 50 MW solar PV power project | Aggregate power | 50 MW (1 × 50 MW) | Data sources | Meteonorm 7.1 [2001-2010] | Land coordinates | Longitude 68°4.2, north latitude 25°19.2, altitude 70 m | Legal time | Time zone TU + 5 | Mounting structure | Fixed tile |
| PV system grid-connected | PV field orientation | PV modules | PV array | Inverter | User’s needs | Tilt 20°, azimuth 0° | Model JKM300P-72 Jinko Solar | No. of module 166680 | Model TC 1000KS | Unlimited load (grid) | Pnom | Pnom total | Pnom | 300 Wp | 50004 kWp | 1000 kW AC | Inverter pack | No. of units: 50.0, Pnom total: 50000 kW AC | PV modules | 8334 strings of 20 modules in series, 50004 kWp total | Area | 323069 m2 | Production | 80085 MWh/year | PR | 77.62% (performance ratio) | No shading field defined |
|
|