Modelling and Assessing the Performance of Hybrid PV-CSP Plants in Morocco: A Parametric Study

Table 4

Summarization of optimal results of each simulation.

Capacity installed: 150 MW

SM11.522.533.54
TES0[1, 4][2, 6][5, 9][7, 12][13, 16][15, 17]
Annual energy (GWh)255[378.8, 392.3][490, 520][592, 640][691, 762][858, 885][960, 973]
LCOE ($/kWh)0.09[0.08, 0.092][0.077, 0.082][0.078, 0.083][0.079, 0.083][0.081, 0.085][0.081, 0.083]