Analyzing Integrated Cost-Schedule Risk for Complex Product Systems R&D Projects
Table 1
Distribution of time and cost for the activities.
| Activities | Number | Time (month) | Cost (million) | a | m | b | a | m | b |
| Project feasibility studies | | 6 | 9 | 12 | 0.50 | 1.00 | 1.50 |
| Program demonstration | | 3 | 6 | 9 | 6.00 | 6.50 | 7.00 |
| Subsystem 1 development | | 2 | 3 | 4 | 0.20 | 0.30 | 0.40 | | 12 | 14 | 16 | 9.00 | 11.00 | 13.00 | | 10 | 12 | 12 | 1.80 | 2.00 | 2.20 |
| Subsystem 2 development | | 1 | 2 | 3 | 0.05 | 0.10 | 0.15 | | 10 | 12 | 14 | 6.00 | 8.00 | 10.00 | | 10 | 12 | 12 | 2.00 | 3.00 | 4.00 |
| Subsystem 3 development | | 2 | 3 | 4 | 0.15 | 0.20 | 0.25 | | 10 | 12 | 14 | 5.00 | 7.00 | 9.00 | | 10 | 12 | 12 | 2.00 | 3.00 | 4.00 |
| Subsystem 4 development | | 1 | 2 | 3 | 0.05 | 0.10 | 0.15 | | 8 | 10 | 12 | 1.30 | 1.50 | 1.70 | | 6 | 10 | 12 | 0.20 | 0.30 | 0.40 |
| Subsystem 5 development | | 1 | 2 | 3 | 0.05 | 0.10 | 0.15 | | 6 | 8 | 10 | 0.90 | 1.00 | 1.00 | | 8 | 10 | 12 | 0.10 | 0.20 | 0.30 |
| Subsystem 6 development | | 1 | 2 | 3 | 0.05 | 0.10 | 0.10 | | 10 | 12 | 14 | 0.60 | 0.80 | 1.00 | | 10 | 12 | 12 | 0.10 | 0.20 | 0.30 |
| System assembly | | 2 | 4 | 6 | 0.30 | 0.40 | 0.50 |
| Integrated testing | | 9 | 12 | 15 | 800 | 1000 | 1200 |
|
|