Analyzing Integrated Cost-Schedule Risk for Complex Product Systems R&D Projects

Table 1

Distribution of time and cost for the activities.

ActivitiesNumberTime (month)Cost (million)
a m b a m b

Project feasibility studies 69120.501.001.50

Program demonstration 3696.006.507.00

Subsystem 1 development 2340.200.300.40
1214169.0011.0013.00
1012121.802.002.20

Subsystem 2 development 1230.050.100.15
1012146.008.0010.00
1012122.003.004.00

Subsystem 3 development 2340.150.200.25
1012145.007.009.00
1012122.003.004.00

Subsystem 4 development 1230.050.100.15
810121.301.501.70
610120.200.300.40

Subsystem 5 development 1230.050.100.15
68100.901.001.00
810120.100.200.30

Subsystem 6 development 1230.050.100.10
1012140.600.801.00
1012120.100.200.30

System assembly 2460.300.400.50

Integrated testing 9121580010001200