Load rate.

Substation numberConventional algorithm [29]The original WVD [30]Transportation model

10.860.760.80
20.720.720.87
30.820.850.87
40.980.780.81
50.880.840.87
60.760.760.87
70.840.840.87
80.910.630.87
90.930.790.87
100.860.850.77
110.890.640.87
120.860.870.81
130.880.630.80
140.890.800.87
150.900.730.80
160.710.870.87
170.900.750.87
180.870.820.85
190.870.790.82
200.530.710.87
210.850.860.87
220.900.750.84
230.78
240.83

Cost (million dollars)157.58157.12146.98
Running Time of the Program (s)8945

Conditions: Windows XP Core (TM) 2 Duo CPU 2.0 GHz RAM 2.0 GB.