Comparison of a Fuzzy Genetic and Simulated Annealing Algorithm Approach for Project Time-Cost Tradeoff

Table 1

Activities, time, costs, and relationships for the considered project network.

ActivityDescriptionDepends onNormal time (days)Crash time (days)Normal cost (EUR)Crash cost (EUR)

AConceptual design for the complex of Main Postal Center (MPC) of Belgrade ā€”907037005000

BTechnical-technological concept of MPC Belgrade complexā€”302529003200

CProviding all necessary terms and agreements for communal connectionsA12010050006500

DConducting an open public acquisition procedure for the service of technological documentation produced for MPC Belgrade constructionB606010001000

EMaking the investment-technical documentation for construction of MPC BelgradeC, D12011035223003700000

FMaking the investment-technical documentation for construction of MPC NisC, D60552360029200

GMaking the investment-technical documentation for construction of MPC Novi SadC, D120100153400160000

HMaking the technological conceptionC, D9080362850387300

IConstruction of MPC BelgradeE3603201561612015970000

JReconstruction of MPC NisF12011010773401090750

KReconstruction and upgrading of MPC Novi SadG36032014372401500000

LEquip the objects: office equipment I, J, K, H90801180015000

MEquip the objects: technological equipmentI, J, K, H100801530018000

NEquip the objects: IT equipmentI, J, K, H806059007000

OInstalling the equipment for automatic sorting of letter postsL, M, N12011078600008000000

PInstalling the equipment for automatic sorting of printed matters (flats)L, M, N27024089500009160000

QInstalling the equipment for automatic sorting of packetsL, M, N12010067747006944000

RInstalling the IT and telecommunication equipmentO, P, Q120901180013200