Research Article

Using Metric Distance Ranking Method to Find Intuitionistic Fuzzy Critical Path

Table 1

Activity duration of each activity in an (Atanassov) intuitionistic fuzzy project network.

Activity Description(Atanassov) Intuitionistic fuzzy activity duration

1-2Inspection of boiler by boiler engineer and preparation of list of parts to be replaced(12, 14, 16, 18); (10, 15, 16, 18)
1-3Placing the order and purchasing(4, 10, 14, 18); (6, 10, 12, 14)
1-4Dismantling of the defective parts from the boiler(8, 16, 20, 24); (9, 13, 15, 17)