Using Metric Distance Ranking Method to Find Intuitionistic Fuzzy Critical Path

Table 2

Total slack (Atanassov) intuitionistic fuzzy time for each activity in an (Atanassov) intuitionistic fuzzy project network and critical path for membership function.

Activity ()
Duration

1-2(12, 14, 16, 18)(0, 0, 0, 0)(−1, 18, 35, 58)(−38, −12, 12, 38)
1-3(4, 10, 14, 18)(0, 0, 0, 0)(−14, 9, 25, 46)(−28, −2, 19, 44)
1-4(8, 16, 20, 24)(0, 0, 0, 0)(−20, 8, 28, 52)(−17, 5, 25, 45)
2-6(5, 10, 15, 20)(12, 14, 16, 18)(19, 33, 45, 63)(−38, −12, 12, 38)
3-5(12, 13, 15, 18)(4, 10, 14, 18)(4, 24, 38, 58)(−28, −2, 19, 44)
4-5(6, 10, 16, 24)(8, 16, 20, 24)(4, 24, 38, 58)(−38, −12, 12, 38)
4-6(13, 15, 17, 20)(8, 16, 20, 24)(19, 33, 45, 63)(−25, −4, 14, 42)
5-6(5, 7, 9, 15)(14, 26, 36, 48)(19, 33, 45, 63)(−44, −12, 12, 44)