Using Metric Distance Ranking Method to Find Intuitionistic Fuzzy Critical Path

Table 3

Total slack (Atanassov) intuitionistic fuzzy time for each activity in an (Atanassov) intuitionistic fuzzy project network and critical path for nonmembership function.

Activity () 
Duration

1-2(10, 15, 16, 18)(10, 15, 16, 18)(−22, −7, 7, 22)(−30, −8, 8, 30)
1-3(6, 10, 12, 14)(6, 10, 12, 14)(−22, −7, 7, 22)(−30, −9, 9, 30)
1-4(9, 13, 15, 17)(9, 13, 15, 17)(−22, −7, 7, 22)(−30, −9, 9, 30)
2-6(12, 14, 15, 17)(16, 25, 32, 38)(−1, 10, 18, 26)(−27, −8, 8, 27)
3-5(16, 18, 20, 22)(10, 15, 20, 24)(−20, −7, 4, 16)(−28, −1, 9, 28)
4-5(1, 2, 5, 7)(10, 15, 20, 24)(−5, 8, 20, 31)(−28, −10, 10, 28)
4-6(11, 15, 18, 19)(16, 25, 32, 38)(−5, 8, 20, 31)(−34, −13, 9, 32)
5-6(6, 10, 12, 14)(16, 25, 32, 38)(2, 13, 22, 32)(−30, −9, 9, 30)