Predicting Freeway Work Zone Delays and Costs with a Hybrid Machine-Learning Model

Table 2

Work zone characteristics of case studies.

Case  1Case  2Case  3

RouteI-78 WBNJ-21 SBI-280 EB
Number of lanes332
Milepost47.3–49.34.2–4.514.1–14.3
Work zone length (km)3.60.50.3
Starting time11 PM, 10/201510 AM, 11/201510 AM, 12/2015
Ending time6 AM, 10/20153 PM, 11/20153 PM, 12/2015
Duration (hours)755
Number of closed lanes21
with SVM (vph)1,5243,2223,798
with HCM (vph)1,3952,9763,910

Note. closure.