Highway Project Value of Money Assessment under PPP Mode and Its Application

Table 5

The estimated investment risks scenario of probabilistic methods,   unit: million Yuan.

ScenarioRisk consequencesProbabilityWeighted

favorableMore than 5% construction cost savings5%-5.24
BasicConstruction cost savings 5% - cost overruns 5%10%0
UnfavorableConstruction cost overruns 5% -15%50%104.82
PoorConstruction cost overruns 15% -25%25%91.72
WorstMore than 25% of construction cost overruns10%52.41
Weighted average243.71