Research Article

Highway Project Value of Money Assessment under PPP Mode and Its Application

Table 6

The financial risks scenario of probabilistic methods,   unit: million Yuan.

scenarioRisk consequencesProbabilityWeighted

favorableMore than 20% higher than the estimated value20%-5076
BasicAs same as estimated value40%0
Unfavorable10% lower than the estimated value20%2538
Poor20% lower than the estimated value10%2538
WorstMore than 30% lower than the estimated value10%3807
Weighted average3807