Research Article

Robust Train Scheduling Problem with Optimized Maintenance Planning on High-Speed Railway Corridors: The China Case

Table 6

Scenarios setting example: downstream of high-speed railway.

SectionRunning time(min)Scenario 1Scenario 2......Scenario 9Scenario 10

1(35, 49)35+·(49-35)35+·(49-35)......35+·(49-35)35+·(49-35)
2(33, 41)33+·(41-33)33+·(41-33)......33+·(41-33)33+·(41-33)
3(50, 68)50+·(68-50)50+·(68-50)......50+·(68-50)50+·(68-50)
4(39, 50)39+·(50-39)39+·(50-39)......39+·(50-39)39+·(50-39)
5(70, 86)70+·(86-70)70+·(86-70)......70+·(86-70)70+·(86-70)
6(39, 50)39+·(50-39)39+·(50-39)......39+·(50-39)39+·(50-39)
7(45, 60)45+·(60-45)45+·(60-45)......45+·(60-45)45+·(60-45)
8(30, 42)30+·(42-30)30+·(42-30)......30+·(42-30)30+·(42-30)
9(34, 42)34+·(42-34)34+·(42-34)......34+·(42-34)34+·(42-34)
10(56, 67)56+·(67-56)56+·(67-56)......56+·(67-56)56+·(67-56)
11(49, 63)49+·(63-49)49+·(63-49)......49+·(63-49)49+·(63-49)

: scenarios parameters.
; ; ; ; ;
; ; ; ; .