Engaging Multiple Actors in Large-Scale Transport Infrastructure Project Appraisal: An Application of MAMCA to the Case of HS2 High-Speed Rail
Table 6
Calculations for assessment example in Figure 3. Calculations based on Olson et al. [
24].
| (j,k) | HS2 | WCML | M1 | | | |
| HS2 | 0 | 8 | 2 | | | | WCML | -8 | 0 | -6 | | | | M1 | -2 | 6 | 0 | | | |
| | HS2 | WCML | M1 | Assessment | Results (geomean) | Normalized |
| HS2 | 1 | 256 | 4 | HS2 | 10.07937 | 79.8% | WCML | 0.00390625 | 1 | 0.015625 | WCML | 0.039373 | 0.3% | M1 | 0.25 | 64 | 1 | M1 | 2.519842 | 19.9% | | | | | ∑ | 12.63858 | 100% |
|
|