Integrating Frequency Setting, Timetabling, and Route Assignment to Synchronize Transit Lines
Table 2
Numerical results for scenarios A.
Costs ($)
Operation
3,407,611
2,773,100
2,773,100
2,111,767
2,111,767
Trips
68,234
68,234
68,499
68,234
68,308
Walk
1,120
1,120
1,097
1,120
1,471
Holding
0
0
0
389
356
First wait
46,464
18,424
19,238
37,422
26,462
Transfer wait
6,125
3,531
2,218
6,293
5,224
Total Cost
3,529,554
2,864,409
2,864,152
2,225,225
2,213,588