Research Article

An Exact Solution Approach for the Bus Line Planning Problem with Integrated Passenger Routing

Table 9

Impact of the Direct Link Network instead of the Change and Go network representation on the exact algorithm.

Number of linesMax nodes per lineNetwork modelCPU time (s)Solutions checked (M)

48DLN29715
CNG137715
8DLN16190225704
CNG>86400>125
12DLN163201044
CNG>86400>69

414DLN16844
CNG327744
8DLN203595013
CNG>86400>165
12DLN460674036
CNG>86400>29