Automatic Guided Vehicles Introduction Impacts to Roll-On/Roll-Off Terminals: Simulation and Cost Model Analysis

Table 2

Results for AGV loading system scenario 1. The simulation results are reported in the same way as in Figure 4 and we tested 10–40 AGVs.

Number of AGVs employedTotal loading time (s)Reduction rate for the loading time compared with the previous number of AGVs (%)Average waiting time within the external ramp (s)

10267,469.000.1728
11243,316.00−9.030.2207
12223,131.00−8.300.3075
13206,215.00−7.580.3487
14191,658.00−7.060.4306
15179,118.00−6.540.5182
16168,065.00−6.170.6281
17158,403.00−5.750.7933
18149,761.00−5.460.9676
19142,008.00−5.181.1023
20135,208.00−4.791.3167
21129,067.00−4.541.6814
22123,464.00−4.341.9076
23118,218.00−4.252.0848
24113,642.00−3.872.4887
25109,490.00−3.652.9827
26105,628.00−3.533.3725
27102,098.00−3.344.2814
2899,278.00−2.765.7039
2996,806.00−2.497.4914
3094,520.00−2.369.3743
3192,593.00−2.0411.8527
3290,984.00−1.7414.9762
3389,737.00−1.3718.3850
3489,063.00−0.7523.2587
3588,376.00−0.7727.2625
3688,117.00−0.2932.9849
3787,877.00−0.2738.2575
3887,626.00−0.2943.9438
3987,475.00−0.1749.4631
4087,394.00−0.0954.4195