Research Article

A Novel Resource-Leveling Approach for Construction Project Based on Differential Evolution

Table 2

Project information.

ActivityDurationPredecessorResource demand

11ā€‰ā€‰0
21015
3512
41513
5312
61012
71526
87310
9356
10352
11252
1234, 10, 116
132101
1428, 125
15312, 132
161146
171157
181167
1947, 9, 17, 1813
20215, 189
212194
221206
233218
241223
25423, 248
262257
272565
283236
293232
303269
3133010
323303
33227, 29, 304
341320
354331
36334, 3512
3733612
38328, 31, 373
39528, 31, 378
401362
41338, 39, 4010
421413
436423
441430