Initial production plan and daily events.

TimeProduction plans and events occurred

10:10:49Production begins (# of order: 20/# of inventory: 10/# of production: 0)
12:53:01Additional order comes (# of additional order: 4, # of total order: 24)
13:00Additional inventory comes (# of additional order: 6)
14:30Additional inventory comes (# of additional order: 6)
19:00Expected production finish time