Research Article

Effects of Physical Sample Approval Practice on Performance and Competitiveness of Export-Oriented Garment Industries in Ethiopia

Table 2

Company B, date-wise sample approval data taken from five different orders.

Order no.Photo sampleSize set samplePreproduction sampleProduction sampleShipment sample
Sending dateApproved dateSending dateApproved dateSending dateApproved dateSending dateApproved dateSending dateApproved date

111/03/201903/04/201910/04/201929/04/201916/05/201914/06/201925/06/201918/07/201929/08/201919/09/2019
209/01/201930/01/201905/02/201922/02/201928/02/201920/03/201901/04/201922/04/201913/07/201927/07/2019
304/03/201901/04/201903/04/201928/04/201904/05/201926/05/201902/06/201922/06/201911/07/201928/07/2019
406/02/201902/03/201906/03/201928/03/201901/04/201927/04/201902/05/201923/05/201924/07/201901/08/2019
521/05/201929/06/201903/07/201930/07/201905/08/201923/08/201928/08/201924/09/201915/11/201930/11/2019
Mean27 days22 days23 days22 days15 days
Total lead time in days = 109