Assessing the Causes of Time Overrun in Building and Road Construction Projects: The Case of Addis Ababa City, Ethiopia

Table 4

The overall ranking of the factors.

SNInfluencing factorsRIIRankGroup/Category

1Reluctance of consultants0.8431Consultant related
2Inaccurate estimation of contract period0.8362Client related
3Delay in approvals and late decision making0.8213Client related
4Slow mobilization of labor0.8094Labor related
5Some tendering maneuvers by contractors0.7495Contractor related
6Slow response and poor inspection0.7396Consultant related
7Delay in payment to supplier/subcontractor0.7167Financial related
8Inflation/prices fluctuation0.7088External Env’t related
9Poor procurement of materials0.7039Material related
10Problem with neighbors (right of way issue)0.70110External Env’t related
11Incomplete drawing/detail design0.69911Consultant related
12Poor site management and supervision0.68212Contractor related
13Change in the scope of the project0.67913Client related
14Late issuance of required permits to work0.67913Gov’t authorities related
15Unforeseen ground condition0.67414External Env’t related
16Government authorities and bureaucracy0.66515Gov’t authorities related
17Inadequate monitoring and control procedures0.65316Consultant related
18Shortage of construction materials0.65316Material related
19Lack of technical knowledge by client0.65117Client related
20Client’s interference0.65028Client related
21Inadequate consultant experience0.64819Consultant related
22Client’s financial difficulties0.64819Financial related
23Problem with neighbors0.63820Social and economic related
24Frequent equipment breakdown0.63221Equipment related
25Availability of required materials, manpower0.63122Social and economic related
26Delay in connecting utilities0.63122Gov’t authorities related
27Escalation of material prices0.61923Material related
28Inadequate contractor experience0.61524Contractor related
29Absenteeism0.61225Labor related
30Shortage of equipment parts0.61026Equipment related
31Complexity of engineering design0.60227Consultant related
32High interest rate0.59528Financial related
33Deficiencies in drawings and specifications0.58529Consultant related
34Nonproductivity of labor and equipment0.57830Contractor related
35Contractor’s financial difficulties0.57631Financial related
36Culture and traditional conflicts0.57432Social and economic related
37Low labor productivity0.57333Labor related
38Issues and conflicts among workers0.57333Social and economic related
39Absence of supervision staff from the site0.56834Consultant related
40Equipment allocation problem0.56834Equipment related
41Rework due to mistakes in construction0.56435Contractor related
42Coordination issues and quality of work0.56236Contractor related
43Slow mobilization of equipment0.55737Equipment related
44Changes in requirements and regulations0.55638Gov’t authorities related
45Change orders0.55439Client related
46Dispute of subcontractors and consultants0.55040Contractor related
47Slow site clearance0.54941External Env’t related
48Unreliable suppliers0.54442Material related
49Contractor management incompetency0.53043Contractor related
50Shortage of skilled labor0.52644Labor related
51Insufficient number of equipment0.52644Equipment related
52No incentives to contractors0.50145Client related
53Low motivation/morale0.50145Labor related
54Inadequate fund allocation0.49646Financial related