SN | Influencing factors | RII | Rank | Group/Category |
|
1 | Reluctance of consultants | 0.843 | 1 | Consultant related |
2 | Inaccurate estimation of contract period | 0.836 | 2 | Client related |
3 | Delay in approvals and late decision making | 0.821 | 3 | Client related |
4 | Slow mobilization of labor | 0.809 | 4 | Labor related |
5 | Some tendering maneuvers by contractors | 0.749 | 5 | Contractor related |
6 | Slow response and poor inspection | 0.739 | 6 | Consultant related |
7 | Delay in payment to supplier/subcontractor | 0.716 | 7 | Financial related |
8 | Inflation/prices fluctuation | 0.708 | 8 | External Env’t related |
9 | Poor procurement of materials | 0.703 | 9 | Material related |
10 | Problem with neighbors (right of way issue) | 0.701 | 10 | External Env’t related |
11 | Incomplete drawing/detail design | 0.699 | 11 | Consultant related |
12 | Poor site management and supervision | 0.682 | 12 | Contractor related |
13 | Change in the scope of the project | 0.679 | 13 | Client related |
14 | Late issuance of required permits to work | 0.679 | 13 | Gov’t authorities related |
15 | Unforeseen ground condition | 0.674 | 14 | External Env’t related |
16 | Government authorities and bureaucracy | 0.665 | 15 | Gov’t authorities related |
17 | Inadequate monitoring and control procedures | 0.653 | 16 | Consultant related |
18 | Shortage of construction materials | 0.653 | 16 | Material related |
19 | Lack of technical knowledge by client | 0.651 | 17 | Client related |
20 | Client’s interference | 0.650 | 28 | Client related |
21 | Inadequate consultant experience | 0.648 | 19 | Consultant related |
22 | Client’s financial difficulties | 0.648 | 19 | Financial related |
23 | Problem with neighbors | 0.638 | 20 | Social and economic related |
24 | Frequent equipment breakdown | 0.632 | 21 | Equipment related |
25 | Availability of required materials, manpower | 0.631 | 22 | Social and economic related |
26 | Delay in connecting utilities | 0.631 | 22 | Gov’t authorities related |
27 | Escalation of material prices | 0.619 | 23 | Material related |
28 | Inadequate contractor experience | 0.615 | 24 | Contractor related |
29 | Absenteeism | 0.612 | 25 | Labor related |
30 | Shortage of equipment parts | 0.610 | 26 | Equipment related |
31 | Complexity of engineering design | 0.602 | 27 | Consultant related |
32 | High interest rate | 0.595 | 28 | Financial related |
33 | Deficiencies in drawings and specifications | 0.585 | 29 | Consultant related |
34 | Nonproductivity of labor and equipment | 0.578 | 30 | Contractor related |
35 | Contractor’s financial difficulties | 0.576 | 31 | Financial related |
36 | Culture and traditional conflicts | 0.574 | 32 | Social and economic related |
37 | Low labor productivity | 0.573 | 33 | Labor related |
38 | Issues and conflicts among workers | 0.573 | 33 | Social and economic related |
39 | Absence of supervision staff from the site | 0.568 | 34 | Consultant related |
40 | Equipment allocation problem | 0.568 | 34 | Equipment related |
41 | Rework due to mistakes in construction | 0.564 | 35 | Contractor related |
42 | Coordination issues and quality of work | 0.562 | 36 | Contractor related |
43 | Slow mobilization of equipment | 0.557 | 37 | Equipment related |
44 | Changes in requirements and regulations | 0.556 | 38 | Gov’t authorities related |
45 | Change orders | 0.554 | 39 | Client related |
46 | Dispute of subcontractors and consultants | 0.550 | 40 | Contractor related |
47 | Slow site clearance | 0.549 | 41 | External Env’t related |
48 | Unreliable suppliers | 0.544 | 42 | Material related |
49 | Contractor management incompetency | 0.530 | 43 | Contractor related |
50 | Shortage of skilled labor | 0.526 | 44 | Labor related |
51 | Insufficient number of equipment | 0.526 | 44 | Equipment related |
52 | No incentives to contractors | 0.501 | 45 | Client related |
53 | Low motivation/morale | 0.501 | 45 | Labor related |
54 | Inadequate fund allocation | 0.496 | 46 | Financial related |
|