Research Article
Planning of Hybrid Micro-Hydro and Solar Photovoltaic Systems for Rural Areas of Central Java, Indonesia
Table 7
The optimal power plant systems.
| Number | Optimal parameters | Value |
| 1 | Capacity of PV (kW) | 0 | 2 | Capacity of micro-hydro (kW) | 555 | 3 | S4KS25P | 0 | 4 | Capacity of converter (kW) | 0 | 5 | Capacity of grid (kW) | 1000 | 6 | Initial capital (US $) | 1,132,426 | 7 | Operating cost (US $/year) | −53,219 | 8 | NPC (US $) | −1,732,441 | 9 | COE (US $/kWh) | −0.139 | 10 | Grid sales (kWh/year) | 3,819,127 | 11 | Renewable fraction | 1 |
|
|