AHP-FSE-Based Risk Assessment and Mitigation for Slurry Balancing Shield Tunnel Construction
Table 1
Construction stage division and content of slurry balancing shield.
Stage division
Overview
Main construction operation content
Stage I
Preconstruction preparation
(1) Site preparation. Construction site, living and production facilities, and pipeline relocation (2) Technical preparation. Construction organization and scheme, and pile measurement (3) Human, machine, and material preparation. Construction team, facility inspection, and materials inspection
Stage II
Working well and shield preparation
(1) Enclosure, drainage, and support for working well (2) Shield-related preparation shield machine transportation, pipe transportation, and slurry separation field
Stage III
Shield construction
Shield machine installation, test tunneling, and normal operation
Stage IV
Internal and auxiliary structure
(1) Inner structure (2) Mechanical and electrical (3) Accessory structure
Stage V
Clean and recovery
Internal structure cleaning, site cleaning, traffic, and greening restoration