Research Article
AHP-FSE-Based Risk Assessment and Mitigation for Slurry Balancing Shield Tunnel Construction
Table 6
First-layer index scores.
| | | Personnel risk | Mechanical risk | Material risk | Method risk | Environmental risk |
| Personnel risk | 1 | 2 | 3 | 2 | 1/3 | Mechanical risk | 1/2 | 1 | 2 | 1/2 | 1/5 | Material risk | 1/3 | 1/2 | 1 | 1/3 | 1/6 | Method risk | 1/2 | 2 | 3 | 1 | 1/4 | Environmental risk | 3 | 5 | 6 | 4 | 1 |
|
|