Research Article

AHP-FSE-Based Risk Assessment and Mitigation for Slurry Balancing Shield Tunnel Construction

Table 8

Single-factor evaluation results.

FactorsRisk level
LargeRelatively largeNormalRelatively smallSmall

Working experience00.40.150.20.25
Safety skills0000.30.7
Emergency capacity00.10.250.150.5
Safety consciousness0.30.30.10.150.15
Working strength000.40.30.3
Physical health000.10.250.65
Sense of discipline000.150.350.5
Working pressure0.30.20.150.10.25
Mechanical failure condition000.150.30.55
Mechanical aging condition00.050.10.450.4
Mechanical wear condition000.20.50.3
Qualification rate of installation0000.350.65
Qualification rate of maintenance0000.250.75
Physical property0000.350.65
Dimensional discrepancy0.050.10.40.250.2
Storage conditions00.050.20.250.5
Stacking condition0.10.150.50.10.15
Integrity degree000.250.30.45
Executive capacity0.050.10.20.20.45
Implementation effect00.050.050.30.6
Working method000.10.350.55
Drawings change0000.250.75
Geological conditions0.250.30.10.20.15
Geological disaster situation0000.050.95
Surrounding traffic conditions000.050.150.8
Settlement level of surrounding buildings0000.050.95
Underground pipeline relocation00.050.10.40.45
Safety facilities0.250.250.150.20.15
Water pollution00.050.150.450.35