Research Article

[Retracted] Real-Time Data Scheduling of Flexible Job in Papermaking Workshop Based on Deep Learning and Improved Fuzzy Algorithm

Table 3

Description of variables.

VariableExplain

Paper serial number, ( is the number of paper)
Process number of paper , ( is the number of processes)
Machine serial number, ( is the total number of machines)
Processing time of the -th process of paper on machine
The start time of the -th process of paper on machine
Completion time of the -th process of paper on machine
Completion time of all paper on machine
Final finish time for all paper
Delivery time of paper
Penalty coefficient for early completion of paper
Penalty coefficient for delayed completion of paper