Investment Decision Support for Engineering Projects Based on Risk Correlation Analysis
Table 4
Basic data from Feb. 2003 to Sep. 2003 of section F in the contract.
| Time | No. of | Monthly Plan | Monthly | Overall | Completion Rate | Contract Price after Change (million Yuan) | Month | Completion | Completion | (million Yuan) | (million Yuan) | (million Yuan) |
| 2003.2 | 14 | 880.1126 | 597.9812 | 5991.5486 | 0.6800 | 8695.2054 | 2003.3 | 15 | 938.5220 | 717.9559 | 6709.5045 | 0.7650 | 8555.2054 | 2003.4 | 16 | 918.4406 | 530.2455 | 7239.7500 | 0.5800 | 8555.2054 | 2003.5 | 17 | 959.0213 | 630.8527 | 7820.6027 | 0.6578 | 8655.2054 | 2003.6 | 18 | 766.6541 | 218.3175 | 8029.8021 | 0.2848 | 9021.8495 | 2003.7 | 19 | 766.6541 | 259.7389 | 8219.0000 | 0.3388 | 9221.8495 | 2003.8 | 20 | 68.6561 | 391.8619 | 8611.4029 | 0.5860 | 9221.8495 | 2003.9 | 21 | 593.3010 | 182.7692 | 8774.9369 | 0.3080 | 9141.8495 |
|
|