Research Article

A Nonlinear Multiobjective Bilevel Model for Minimum Cost Network Flow Problem in a Large-Scale Construction Project

Table 8

Computation time and memory used by MOBLPSO, MOBLGA and MOBLSA.

TypeCombination of weightsMinimal weight sum value of the two objectivesAverage computation time (min)
MOBLPSOMOBLGAMOBLSAMOBLPSOMOBLGAMOBLSA

11152.0271160.9891152.53120.85625.89934.458
21024.2721032.4191024.27320.92626.03233.921
3896.238903.848897.21421.05225.67934.068
4769.472775.277769.55521.15825.32935.568
5641.786646.706641.89720.96326.16935.012
6514.148518.136514.21620.67826.96935.142
7386.486388.529386.52121.20326.13534.791
8258.792260.836258.79220.73425.47535.291
9131.081132.143131.08121.13426.18934.815