A New Approach to Determine the Critical Path in Stochastic Activity Network
| | The shortest path: | The longest path: |
| Index | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Mean | 40.0 | 50.0 | 45.0 | 54.9 | 30.0 | 35.0 | 40.0 |
| Index | 8 | 9 | 10 | 11 | 12 | 13 | 14 |
| Mean | 25.0 | 30.0 | 40.0 | 50.0 | 26.0 | 28.0 | 20.0 |
| Index | 15 | 16 | 17 | 18 | 19 | 20 | 21 |
| Mean | 25.0 | 30.0 | 20.0 | 18.0 | 36.0 | 45.0 | 15.0 |
| Index | 22 | 23 | 24 | | | | |
| Mean | 59.9 | 25.0 | 46.1 | | | | |
|
|