Branch and Bound Algorithms for Resource Constrained Project Scheduling Problem Subject to Nonrenewable Resources with Prescheduled Procurement

Table 4

Number of instances of each set of group II out of 60 solved to optimality in 20 seconds.

Sample problems setsCPLEX SolverPTAEAAMDAAMFSA

6060605960
6060606060
5660605860
5060564750
3860534834
2755453836
830149