Branch and Bound Algorithms for Resource Constrained Project Scheduling Problem Subject to Nonrenewable Resources with Prescheduled Procurement

Table 5

Results of solving instances of group I categorized by values of parameters —Number of problems of each setting out of 140 solved to optimality in 20 seconds—Average project completion times.

( , )CPLEX SolverPTAEAAMDAAMFSAAverage

(0.5, 0.5)12712612212612349.3
(0.5, 1)10512211810610452.7
(1, 0.5)1051171081009046.6
(1, 1)99117104969148.2
(0.5, 1.5)7011187647572.8
(1.5, 0.5)6411490658168.6
(1, 1.5)5810685506468.6
(1.5, 1)6610684577971.2
(1.5, 1.5)5310582437378.6