Branch and Bound Algorithms for Resource Constrained Project Scheduling Problem Subject to Nonrenewable Resources with Prescheduled Procurement

Table 6

Results of solving instances of group II categorized by number of nonrenewable resources—Number of problems of each setting out of 140 solved to optimality in 20 seconds—Average project completion times.

Number of nonrenewable resourcesCPLEX SolverPTAEAAMDAAMFSAAverage

111012311611611241.9
210111910511010546.5
488116103989048.9