Research Article
Risk Evaluation on UHV Power Transmission Construction Project Based on AHP and FCE Method
Table 10
The weight of risk indicators.
| Criteria layer | Index layer | Indicator | Weight
| Indicator | Local weight
| Global weight
|
| Policy and law risk
| 0.20 | | 0.20 | 0.0400 | | 0.07 | 0.0140 | | 0.37 | 0.0740 | | 0.08 | 0.0160 | | 0.22 | 0.0440 | | 0.06 | 0.0120 |
| Management risk
| 0.22 | | 0.03 | 0.0066 | | 0.07 | 0.0154 | | 0.09 | 0.0198 | | 0.06 | 0.0132 | | 0.04 | 0.0088 | | 0.11 | 0.0242 | | 0.09 | 0.0198 | | 0.06 | 0.0132 | | 0.12 | 0.0264 | | 0.09 | 0.0198 | | 0.03 | 0.0066 | | 0.05 | 0.0110 | | 0.04 | 0.0088 | | 0.04 | 0.0088 | | 0.04 | 0.0088 | | 0.03 | 0.0066 |
| Technology risk
| 0.15 | | 0.14 | 0.0210 | | 0.20 | 0.0300 | | 0.07 | 0.0105 | | 0.06 | 0.0090 | | 0.11 | 0.0165 | | 0.09 | 0.0135 | | 0.13 | 0.0195 | | 0.14 | 0.0210 | | 0.06 | 0.0090 |
| Natural environment risk
| 0.12 | | 0.64 | 0.0768 | | 0.36 | 0.0432 |
| Society risk
| 0.31 | | 0.29 | 0.0899 | | 0.12 | 0.0372 | | 0.24 | 0.0744 | | 0.16 | 0.0496 | | 0.1 | 0.0310 | | 0.09 | 0.0279 |
|
|