Mathematical Model of Hybrid Precast Gravity Frames for Smart Construction and Engineering
Table 6
Comparative analysis of the construction period [
20].
|
Structural type | Construction period |
Comparison | Typical floor | 30-story apartment building |
| Bearing wall | 7 days/1 floor | 210 Days | 100.0% | Hybrid precast frame | 10 days/3 floors | 100 Days | 47.6% |
|
|