Research Article
Engineering Mathematical Analysis Method for Productivity Rate in Linear Arrangement Serial Structure Automated Flow Assembly Line
Table 2
Technical data for final assembly flow line in 31 working shifts.
Title
Data
Total machining time,
(min)
26.55
Auxiliary time,
(min)
0.52
Number of stations,
37
Correction factor for machining time of the bottleneck station
,
1.25