A Hybrid Search Algorithm for Midterm Optimal Scheduling of Thermal Power Plants

Table 3

Results of generation requirements for Plants 1 to 9 in May (MW).

DatePlant 1Plant 2 Plant 3Plant 4Plant 5Plant 6Plant 7Plant 8Plant 9
Virtual plant 1Virtual plant 2Total

1st2400150012004006001000300300300300135
2nd2400150012004006001000600300300300135
3rd24001500900200600800600600600300135
4th24001500900200600800600600600600135
5th24001500900200600800600600600600135
6th24001500120040060010006006006006000
7th24001800120040060010006006006006000
8th24001800120040060010006006006006000
9th2400180012004006001000600600600600135
10th240018001200400300700600300300600135

11th240018001200400300700600300300600135
12th240018001200400300700600300300600135
13th1800180012004006001000600600600600135
14th180018009004006001000600600600600135
15th180015009004006001000600600600600135
16th240012009004006001000300600600600135
17th24009001200200600800300600600600135
18th24009001200200600800300600600300135
19th24009001200200600800300600600300135
20th24009001200400300700600300300300135

21st240012001200400300700600300300300135
22nd240012001200400300700600300300300135
23rd240012001200400300700600300300600135
24th120018003004006001000600600600600135
25th60018003004006001000600600600600135
26th60018003004006001000600600600600135
27th6001800900200600800300600600600135
28th120018009000600600300600600600135
29th120018009000600600300600600600135
30th1200180090006006003006006003000
31st24009009004003007003003003003000