Planning Tunnel Construction Using Markov Chain Monte Carlo (MCMC)
Table 2
Summary of statistical adjustment for unit operation.
|
Unit operation | Parameters |
Probability Distribution | Used data | Mean | Median | Mode | Standard deviation | Coefficient of variability | Minimum | Maximum |
| Drilling | 137 | 195.45 | 193.89 | 190.23 | 38.08 | 0.19 | 70.98 | 392.79 | Beta |
| Load and blasting | 133 | 56.09 | 55.76 | 54.98 | 11.64 | 0.20 | 14.77 | 113.51 | Beta |
| Ventilation | 136 | 90.00 | 90.00 | 90.00 | 0 | — | — | — | Constant |
| Scaling | 135 | 26.08 | 25.24 | 23.54 | 6.77 | 0.25 | 8.04 | — | Lognormal |
| Mucking | 135 | 70.03 | 65.66 | 58.33 | 20.22 | 0.28 | 30.95 | — | Gamma |
|
|