Research Article

An Adapted Firefly Algorithm for Product Development Project Scheduling with Fuzzy Activity Duration

Table 5

Project data for an electronic product development project [1].

Act.
number
Fuzzy duration Resource required
Successors

1(0, 0, 0, 0)00  0  02
2(5, 6, 6, 7)30  0 0 3
3(10, 12, 12, 13)5 3 3 24, 5
4(4, 5, 5, 6)42  4 26
5(7, 8, 8, 10)4 2 2 26
6(2, 4, 4, 6)50  0  07
7(3, 4, 4, 5)42  2 28
8(2, 3, 3, 4)43  3 29, 10, 11, 13
9(2, 3, 3, 5)04  2 014
10(3, 4, 4, 6)21  5 315
11(4, 5, 5, 6)40 0 012
12(7, 9, 9, 10)50 0 016
13(3, 4, 4, 5)30 0 116
14(1, 2, 2, 3)32 0  116
15(1, 2, 2, 3)30 3 216
16(1, 2, 2, 2)42 2217
17(3, 4, 4, 5)52 2 018, 19
18(4, 5, 5, 6)52 4 220
19(4, 5, 5, 6)42 4 320
20(5, 6, 6, 7)52 3  421, 22, 23
21(5, 7, 7, 9)400 024
22(3, 5, 5, 7)51 4  424
23(4, 5, 5, 6)03 0024
24(1, 2, 2, 3)511 125
25(8, 10, 10, 12)215 326, 27, 28
26(4, 5, 5, 6)215 330
27(4, 6, 6, 8)00 4 329
28(6, 7, 7, 8)040 230
29(10, 12, 12, 14)224 430
30(1, 2, 2, 4)42 2 231, 32, 33, 39, 40, 42
31(9, 11, 11, 10)423 034
32(10, 13, 13, 14)503 237
33(8, 10, 10, 11)004 238
34(6, 8, 8, 9)432 035
35(3, 4, 4, 5)423  336
36(4, 6, 6, 7)220 441
37(1, 3, 3, 4)002 041
38(3, 4, 4, 5)002 241
39(1, 2, 2, 3)103 141
40(2, 3, 3, 4)00 2 241
41(1, 1, 1, 2)404 345, 46, 49
42(3, 4, 4, 5)04 0 043
43(1, 2, 2, 3)33 0 044
44(1, 2, 2, 3)303 045, 46
45(3, 4, 4, 5)234 152
46(4, 5, 5, 6)224 247
47(4, 5, 5, 6)52 2 348
48(3, 4, 4, 5)20 4 252
49(5, 7, 7, 8)20 2 350
50(6, 8, 8, 10)423 251
51(2, 3, 3, 5)42 3  352
52(2, 4, 4, 7)42 3 353
53(0, 0, 0, 0) 00 00