Multidimensional and Interactive Assessment Model of Large-Scale Infrastructure Project and Its Demonstration Based on Double Utility
Table 6
Identification and screening matrix of Project A’s main risk factors.
| Risk type | Risk factors | Government regulation change | Insufficient feasibility study | Decision-making mistakes | Major natural disasters or bad weather | Popular opposition | Cost rising | Market demand reduction | Financing difficulties | Design mistakes | Wrong construction procedure or default | Main body violation | Major natural disasters or bad weather | Social security incident | Improper maintenance or updates |
| Technology risk | | | | | | | | | 1 | 1 | | | | 3 | Economic risk | | | | | | 2 | 2 | 2 | | | 1 | | | | Social risk | 1 | | | | 2 | | | | | | | | 2 | | Natural risk | | | | 3 | | | | | | | | 3 | | | Management risk | | 2 | 2 | | | | | | | | | | | | Law risk | | | | | | | | | | | 1 | | 3 | |
|
|
Note: 1, 2, 3: the severity of the risk: 1: grave, 2: severe, 3: serious.
|