Business Impact and Policy on the Major Players in the Market of the Development of Distributed Energy in China

Table 5

The calculation of the beneficial impact on power supply enterprises in S province after access to distributed PV.

YearThe access costThe cost of operation and maintenance and marketing serviceThe benefits impact of access to excess distributed electricityThe benefits impact of the private useThe benefits impact on the grid power supply enterpriseThe benefits impact on the grid power supply enterprise (after tax)

2011 (actual)0.3060.0310.00560.01910.360.27
2012 (actual)1.3440.1340.02470.08371.591.19
2013 (actual)3.2510.3250.05970.20253.842.88
2014 (actual)10.651.0650.19570.663412.579.43
2015 (prediction)181.80.33071.121321.2515.94
2020 (prediction)454.50.82662.803353.1339.85