Research Article

Minimizing Total Earliness and Tardiness for Common Due Date Single-Machine Scheduling with an Unavailability Interval

Table 3

Influence of the proportionality coefficient and the due date factor on the dynamic programming method.

(P, R)nCase 1Case 2Case 3
Time (s)Time (s)Time (s)

(0.25, 0.3)1000.140.09<0.01
3003.162.35<0.01
50015.0311.230.01
70039.4924.580.01
1000130.8782.760.03

(0.25, 0.5)1000.090.08<0.01
3003.082.36<0.01
50016.6910.13<0.01
70036.4625.280.01
1000134.1779.130.03

(0.25, 0.7)1000.110.09<0.01
3003.202.15<0.01
50016.7511.47<0.01
70045.8427.620.01
1000122.9088.580.03

(0.5, 0.3)1000.180.13<0.01
3005.374.99<0.01
50023.1523.05<0.01
70066.2261.520.01
1000201.46185.010.05

(0.5, 0.5)1000.180.24<0.01
3005.255.17<0.01
50028.7522.25<0.01
70069.4360.680.02
1000224.80166.460.04

(0.5, 0.7)1000.160.18<0.01
3005.744.83<0.01
50025.6724.67<0.01
70071.1964.090.02
1000205.13200.980.04

(0.75, 0.3)1000.280.30<0.01
3006.047.71<0.01
50030.9234.930.01
70082.5093.580.02
1000305.83293.250.06

(0.75, 0.5)1000.270.29<0.01
3006.517.70<0.01
50033.7635.080.01
70079.24100.420.03
1000255.73298.250.06

(0.75, 0.7)1000.320.49<0.01
3005.498.68<0.01
50036.8143.540.01
70090.10116.320.02
1000231.43312.970.06