Simulation-Based Optimization for Yard Design at Mega Container Terminal under Uncertainty
Table 2
The decision variables and optimal yard design schemes under various investment budgets.
| Number | Budgets (MCNY/month) | Decision variables | Yard design schemes | Costs (MCNY/month) | | | | Yard depth (m) | Block length (m) | # of yard cranes | Investment cost | Operation losses | Total costs |
| 1 | 5 | 12 | 2 | 1 | 360 | 670 | 12 | 4.69 | 11.01 | 15.70 | 2 | 5.5 | 12 | 3 | 2 | 360 | 440 | 24 | 5.19 | 8.81 | 14.00 | 3 | 6 | 14 | 6 | 2 | 413 | 210 | 28 | 5.98 | 6.82 | 12.80 | 4 | 6.5 | 14 | 6 | 2 | 413 | 210 | 28 | 5.98 | 6.82 | 12.80 | 5 | 7 | 14 | 6 | 3 | 413 | 210 | 42 | 6.57 | 6.19 | 12.76 | 6 | 7.5 | 14 | 6 | 3 | 413 | 210 | 42 | 6.57 | 6.19 | 12.76 |
|
|