Research Article
A Model for Sorting Activities to Be Outsourced in Civil Construction Based on ROR-UTADIS
Table 8
Possible assignments.
| Alternatives | First iteration | Second iteration | Third iteration |
| Concrete | C3 | C3 | C3 | Concrete paving | C3 | C3 | C3 | CFA Stake | C3 | C3 | C3 | Hydroseeding | C3 | C3 | C3 | Earthwork | C2-C3 | C2-C3 | C3 | Transport of personnel | C2-C3 | C2-C3 | C2 | Precast concrete | C2-C3 | C2-C3 | C2 | Form system, shoring, and scaffolding | C2-C3 | C2 | C2 | Heavy equipment | C2 | C2 | C2 | Food supply | C1-C2 | C2 | C2 | Gypsum liner | C1-C2 | C2 | C2 | Asphalt paving | C1 | C1 | C1 | Property security | C1 | C1 | C1 | Vegetal suppression | C1 | C1 | C1 | Containers | C1 | C1 | C1 | Waterproofing | C1 | C1 | C1 | Air conditioning | C1 | C1 | C1 |
|
|