Table 1

Task assignment process for the line configuration (3, 3, 3, 3, 3, 3, 3, 3, 3, 3, 3, 3).

StepStation index (man count)Task with no predecessor (priorities)Selected taskStart timeMan indexNotes

1 1 ()1 ()101
22 (), 3 (), 4 (), 5 ()261
33 (), 4 (), 5 (), 6 (—)462Task 6 cannot be completed before the end of cycle time.
43 (), 5 (), 6 (—)563Task 6 cannot be completed before the end of cycle time.
53 (), 6 (—), 8 (—)381Tasks 6 and 8 cannot be completed before the end of cycle time.
66 (—), 7 (—), 8 (—)(i) Tasks 6, 7, and 8 cannot be completed before the end of cycle time.
(ii) New station is opened.

7 2 () 6 (), 7 (), 8 ()701
86 (), 8 ()802
96 (), 10 (—)603Task 10 cannot be started at time 0.
109 (), 10 (—)942Task 10 cannot be started at time 4.
1110 (), 11 (—)1081Task 11 cannot be completed before the end of cycle time.
1211 (—)(i) Task 11 cannot be completed before the end of cycle time.
(ii) New station is opened.

13 3 ()11 ()1101
1412 ()1261