Research Article

Joint Scheduling Optimization of Virtual Power Plants and Equitable Profit Distribution Using Shapely Value Theory

Table 1

Interruptible load capacity and the maximum continuous time of the three VPPs.

VPPIL

V1#1, 200 Kw, 3 h; #2, 200 Kw, 1 h; #3, 150 Kw, 2 h; #4, 100 Kw, 3 h
V2#5, 200 Kw, 1 h; #6, 250 Kw, 6 h; #7, 200 Kw, 2 h
V3#8, 300 Kw, 3 h; #9, 100 Kw, 3 h