Ordering Strategy Analysis of Prefabricated Component Manufacturer in Construction Supply Chain
Table 1
Reinforcement demand of a prefabricated component.
| Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 |
| Demand (t) | 50 | 20 | 60 | 0 | 30 | 20 | 70 | 35 | 53 | 74 | 59 | 22 | 43 | 44 | 24 | 58 | 22 | 52 | 37 | 48 | 0 | 48 | 52 | 35 | Time () | 1–3 | 3-4 | 4–8 | 8-9 | 9-10 | 10–13 | 13–15 | 15-16 | 16–18 | 18–21 | 21–24 | 24-25 | 25–28 | 28–30 | 30-31 | 31–34 | 34-35 | 35–38 | 38–40 | 40–43 | 43-44 | 44–47 | 47–50 | 50–52 | Duration () | 2 | 1 | 4 | 1 | 1 | 3 | 2 | 1 | 2 | 3 | 3 | 1 | 3 | 2 | 1 | 3 | 1 | 3 | 2 | 3 | 1 | 3 | 3 | 2 |
|
|